OB702 Roscommon Bridge Widening & Road Alignment

The existing bridge OB702 was widened to take the skew out of the road. The overbridge comprised of Opti-Cadre units and reinforced earth abutments.

The bridge was widened to the Claremorris side by approximately 10.5m while leaving the existing structure intact and maintaining traffic flow. The reinforced earth walls were constructed with little interference to the existing passing traffic and the railway line. Other works included palindine fencing, high level safety barrier and road surfacing. The work was necessary to create a straight road across the railway line to enable all local traffic to traverse the bridge safely. This project was the first of its type to use Opti-Cadre units to extend an existing bridge.

please follow link below to see installation of precast concrete portal frame:

https://www.conneelybuilders.com/video-gallery/?catid=cat1&slg=ob-702-roscommon

Single Lane Carriageway, Kilnockin. Mallow, Co. Cork

At this site, Iarnród Éireann manned level crossing number XC227 was replaced by a single lane carriageway with associated works, Dismantling and removal of a steam engine water storage tower, decommissioning of diesel storage tanks, palisade fencing, concrete block boundary wall, reinforced concrete ballast retaining wall, drainage, earthworks, kerbing, lighting, footpaths, landscaping, tarmacadam and surface dressing. Construction was phased in stages to facilitate access to Iarnród Éireann yards and minimise disruption to local traffic.

Access Road at Bishopswood, Dundrum, Co. Tipperary

At this site, Iarnród Éireann manned level crossing number XC128 was replaced by an access road with associated works, boundary treatment, timber post and rail fencing, drainage, filling and surface dressing. Extensive site clearance of existing trees through Coillte owned lands was carried out. The roadway was constructed on very poor ground using geotextiles and geogrid. The geogrid used here was Enkagrid Pro 90 which worked well with the poor ground conditions. The existing level crossing gates were replaced with blockwork wall & a double palisade access gate. A precast concrete culvert, supplied by Banagher Concrete, was installed to replace an existing culvert crossing the new access road.

Noone’s UB121, Rineen, Gort, Co. Galway

At this site Existing Level Crossing’s XE128 & XE129 were closed and replaced by a 4.50m x 4.50m internal dimension under-bridge, 20m long. The under-bridge was a contractor designed structure.

500m long new access roads were also constructed The installation of the under-bridge took place over 2 days, from 7.00 am Tuesday 16th of June 2009 to 6.00pm on Wednesday 17th of June 2009. The under-bridge is made up of 15no U shaped duct units each weighing approx 20t (i.e. 8no base units and 7no top units). A 350 ton crane was used during the installation both for lifting /replacing the track and also for installing the units.

On day 1, the track was removed, excavation completed, and preparation of base for unit’s. On day 2 the precast units were installed. All sealants and waterproof membranes installed and completion of stitches between units together one erection of temporary handrails.

Please follow link below to see video of precast units being lifted into place:

https://www.conneelybuilders.com/video-gallery/?catid=cat1&slg=installation-of-precast-concrete-underpass-at-gort

Portiuncula Hospital Car Park, Ballinasloe, Co. Galway

Construction of 400 space carpark at Portiuncula Hospital, Ballinasloe, Co.Galway, including installation of public lighting, drainage, 700m of palisade fencing and landscaping.

Geoghegans OBE 151a

This project involved the closure of two number Iarnród Eireann Level Crossing’s. The crossings were replaced by a single overbridge and associated approach embankments. The overbridge comprised of a contractor designed structure and contractor designed reinforced earth wing walls. Construction of the new Overbridge consisted of Precast Optri-Cadre units each weighing 36 tonnes and included precast concrete parapet units. A new access road with concrete post and wire fencing was constructed over a length of 1,200m to tie into the existing public road at one end and farm access road at the other end.

Havertys OB158A

This project involved the closure of three number Iarnród Eireann Level Crossing’s. The crossings were replaced by a single overbridge and associated approach embankments. The overbridge comprised of a contractor designed structure and contractor designed reinforced earth wing walls. Construction of the new Overbridge consisted of 11.50m wide Precast Optri-Cadre units each weighing 36 tonnes and included precast concrete parapet units. The existing level crossing gates were taken down and closed to traffic. The new road was 4 metres wide with concrete post and wire fencing, and constructed over a length of 650m to tie into existing farmer access roads.

Caherduff OB142A

This project involved the closure of two number Iarnród Eireann Level Crossing’s. The crossings were replaced by a single overbridge and associated approach embankments. The overbridge comprised of a contractor designed structure and contractor designed reinforced earth wing walls. Construction of the new Overbridge consisted of 11.50m wide Precast Optri-Cadre units each weighing 36 tonnes and included precast concrete parapet units. The existing level crossing gates were taken down and closed to traffic. The new road was 4 metres wide with concrete post and wire fencing, and constructed over a length of approximately 1,000m to tie into existing public roads.

Bachelor’s Walk Residential Development

Bachelors Walk is an exclusive development of quality residential houses built on a prime location at Ard Mhuire, Ballinasloe. The sites are spacious, well laid out and range in size from 1/5 to 1/3 of an acre. The site is overlooked by beautiful trees from the adjoining esker hills and Garbally College with its superb grounds and walks are only a short distance away. The houses range in size from 2700 sq.ft to 4000 sq.ft with the houses comprising of 5 – 7 bedrooms. The development is extensively landscaped and includes a tennis court.

Expansion of Wicklow Station Car Park, Co. Wicklow

Works consisted of the extension of the existing small car park at Wicklow Train Station to include for 77 car spaces, 4 mobility impaired spaces, 3 bus and 18 cycle spaces. The works involved site clearance, earthworks, reinforced concrete retaining wall up to 5m high with Wicklow granite masonry cladding, drainage, electrical ducting, lamp post installation, fencing and line painting. Works were phased to accommodate the continued opening of the existing county council footpath. The majority of the works were carried out from within a hoarding line and there was no works which directly affected railway operations, however the Iarnród Eireann Permanent Way compound was kept accessible to vehicles on a 24 hour basis 7 days a week. Extensive drainage was required which involved a double layer of porous asphalt macadam laid on a reservoir stone layer, herringbone drains and all pipework connected to a full retention petrol interceptor before discharge to river.

OB132 Bridge Renewal, Ballinasloe, Co. Galway

The existing metal deck bridge was replaced with a precast concrete bridge. The works involved the removal of the steel bridge , placing of precast bedstones, beams and retaining wall units. Installation of an Aluminium Bridge parapet , double height crash barrier , fencing, road surfacing , telecom and water diversion. The bridge was assessable to traffic after four days.

Bridge Renewal Project OB121, Ballinasloe, Co. Galway

The existing metal deck bridge was replaced with a pre-cast concrete bridge. Works included removal of the steel bridge, placing pre-cast concrete bed stones, beams and parapet walls. Diversion of existing services, extensive retaining wall structures with faced gabions, permanent fencing, pre-cast concrete safety barriers and accommodation works for local residents.