Nugents 2, UBE 96c, Chipfield, Ennis, Co Clare

Project Description:

At this site located on the Western Rail Corridor we constructed a new under track crossing for the landowner. This consisted of a 3m x 3m box culvert 18.448m long with a 250mm wall which was fully waterproofed upon installation. The works were completed within a 36hr programme to suit the closure of the line for the works.

Works also included associated roadworks, drainage, fencing, closure of XE 70 and landscaping.