Project Description:

This project involved the closure of two number Iarnród Eireann Level Crossing’s. The crossings were replaced by a single overbridge and associated approach embankments. The overbridge comprised of a contractor designed structure and contractor designed reinforced earth wing walls. Construction of the new Overbridge consisted of Precast Optri-Cadre units each weighing 36 tonnes and included precast concrete parapet units. A new access road with concrete post and wire fencing was constructed over a length of 1,200m to tie into the existing public road at one end and farm access road at the other end.


  • _edit_last : 2
  • _edit_lock : 1410083337:2
  • Client : Iarnród Éireann
  • _rawhtml_settings : 0,0,0,0
  • Engineer : Roughan & O’Donovan
  • Engineer : Roughan & O’Donovan