Project Description:

This project involved the closure of two number Iarnród Eireann Level Crossing’s. The crossings were replaced by a single overbridge and associated approach embankments. The overbridge comprised of a contractor designed structure and contractor designed reinforced earth wing walls. Construction of the new Overbridge consisted of 11.50m wide Precast Optri-Cadre units each weighing 36 tonnes and included precast concrete parapet units. The existing level crossing gates were taken down and closed to traffic. The new road was 4 metres wide with concrete post and wire fencing, and constructed over a length of approximately 1,000m to tie into existing public roads.


  • _edit_last : 2
  • _edit_lock : 1410083408:2
  • _rawhtml_settings : 0,0,0,0
  • Engineer : Roughan & O’Donovan
  • Client : Iarnród Éireann
  • _thumbnail_id : 1128